Poudre Ponds Pump Station

Owner: City of Greeley
Designer: Wenck & Associates
Value: $302,857
Award Date: September 25, 2017
Anticipated Completion Date: December 4, 2017

Project Overview:
Installation of new 50 HP vertical turbine pump in the same wetwell as an existing 125 HP pump, modifications to the existing and installation of new discharge piping, installation of a VFD for the new pump, installation of automated pump oil lubrication systems on the new pump and three existing pumps, completing electrical and controls work, pump system testing and start-up, demolition and replacement of approximately 30-feet of 24-inch force main discharge pipe, and furnishing a 2,000 GPM bypass pump during construction.